===== Release schedule for IWM 2015 =====
 
===== Release schedule for IWM 2015 =====
  
WS247 is due on ftp.sanger mid-Feb, so public mid April. If we want WS248 to be live at the meeting, we should be aiming for it to go live by early-mid June. This implies an freeze/upload window of end-Feb to mid-March. Precise dates to be discussed.  
+
WS247 is due on ftp.sanger mid-Feb, so public mid April. If we want WS248 to be live at the meeting, we should be aiming for it to go live by early-mid June. This implies an freeze/upload window of end-Feb to mid-March. Precise dates to be discussed.
 +
 
 +
If we want it live the whole of june we can have a short cycle between 247 and 248
 +
 
 +
13th Feb Models deadline
 +
20th Fen Models Tag models
 +
13th Mar Data upload
 +
3rd Mar 248 FTP'd Hinxton
 +
1st April 248 Staging
 +
1st June 248 Live
 +
 
 +
So as Kevin said there is a sliding 3/4 week window to be decided.
  
 
===== WormMine =====
 
===== WormMine =====

Revision as of 16:21, 5 February 2015

Agenda and minutes

help desk issues

Topics

Release schedule for IWM 2015

WS247 is due on ftp.sanger mid-Feb, so public mid April. If we want WS248 to be live at the meeting, we should be aiming for it to go live by early-mid June. This implies an freeze/upload window of end-Feb to mid-March. Precise dates to be discussed.

If we want it live the whole of june we can have a short cycle between 247 and 248

13th Feb Models deadline 20th Fen Models Tag models 13th Mar Data upload 3rd Mar 248 FTP'd Hinxton 1st April 248 Staging 1st June 248 Live

So as Kevin said there is a sliding 3/4 week window to be decided.