Difference between revisions of "Website:Development Milestones"
From WormBaseWiki
Jump to navigationJump to search(3 intermediate revisions by the same user not shown) | |||
Line 18: | Line 18: | ||
** [https://bitbucket.org/tharris/wormbase/issues?status=open&status=new&milestone=Phase%20II.1:%20Class%20Conversion%20(due:%202011.03.01) Outstanding Issues] | ** [https://bitbucket.org/tharris/wormbase/issues?status=open&status=new&milestone=Phase%20II.1:%20Class%20Conversion%20(due:%202011.03.01) Outstanding Issues] | ||
+ | '''April 1st, 2011''' | ||
+ | * '''Objective 2: unit and UI testing in place; UI refinement and polishing''' | ||
+ | ** [https://bitbucket.org/tharris/wormbase/issues?status=open&status=new&milestone=Phase%20II.2:%20Unit%20and%20UI%20testing%20(due%202011.04.01) Outstanding Issues] | ||
** General development | ** General development | ||
*** Search mechanism; multi-class | *** Search mechanism; multi-class | ||
− | |||
− | |||
− | |||
− | |||
− | |||
'''April 15th, 2011''' | '''April 15th, 2011''' | ||
− | * '''Objective 3: code profiling in place''' | + | * '''Objective 3: code profiling in place; performance tuning''' |
** [https://bitbucket.org/tharris/wormbase/issues?status=new&status=open&milestone=Phase%20II.3:%20Code%20Profiling%20(due%202011.04.15) Outstanding issues] | ** [https://bitbucket.org/tharris/wormbase/issues?status=new&status=open&milestone=Phase%20II.3:%20Code%20Profiling%20(due%202011.04.15) Outstanding issues] | ||
Latest revision as of 20:23, 2 March 2011
Phase III: Launch
December 31st, 2011
- Retire old site
September 1st, 2011
- Launch new site
June 26th, 2011
- Beta launch of new site at International Worm Meeting
Phase II: Iterative Development, Refinement, Testing
March 1st, 2011
- Objective 1: conversion of all existing pages to new structure
April 1st, 2011
- Objective 2: unit and UI testing in place; UI refinement and polishing
- Outstanding Issues
- General development
- Search mechanism; multi-class
April 15th, 2011
- Objective 3: code profiling in place; performance tuning
May 2nd - June 1st, 2011
- Objective 4: UX testing, limited preview
June 1st, 2011
- Objective 5: Production architecture
Phase I
February 1st, 2011
- Preview new site to SAB
December 22nd, 2010
- Begin private review of new site
- Launch surveys on UI
July 30th - August 31st
- Finish API development of critical classes
- Finish migration of prominent CGI-based pages to new architecture and release into production (classic view only)
- Solidify look-and-feel of new site: site map, browsing paths, design patterns, navigation
- UI features to address/develop
- Enhanced, high-performance search
- External URL handling
- Error trapping and reporting
- Authorization/Authentication
- Customizability
- Configurable two-panel selector
- Incorporation of old site elements like BLAST/BLAT
- Top-level species pages (/celegans, eg) and UI clues for distinguishing them
July 14 - July 30th
- Coronate Czars
- Coding standards and best practices for CSS, Javascript, API in place
- Release new pages to production powered by the new architecture (classic view only)
- Variation, Protein, Sequence -- and maybe -- Gene
- Todd to develop <strikethrough>deployment strategy</strikethrough>, hosting environment, and proxy configuration
- Abby and Xiaoqi to work up templates and markup specific to the classic view
- Norie to make requisite API changes as needed