Line 18: Line 18:
 
* [https://bitbucket.org/tharris/wormbase/issues?status=open&status=new&milestone=Phase%20II.1:%20Class%20Conversion%20(due:%202011.03.01) Outstanding Issues]
 
* [https://bitbucket.org/tharris/wormbase/issues?status=open&status=new&milestone=Phase%20II.1:%20Class%20Conversion%20(due:%202011.03.01) Outstanding Issues]
  
===== April 1st, 2011 =====
+
==== April 1st, 2011 ====
  
 
'''Objective 2: unit and UI testing in place'''
 
'''Objective 2: unit and UI testing in place'''
 +
* [https://bitbucket.org/tharris/wormbase/issues?status=open&status=new&milestone=Phase%20II.2:%20Unit%20and%20UI%20testing%20(due%202011.04.01) Outstanding Issues]
  
 
===== April 15th, 2011 =====
 
===== April 15th, 2011 =====

Revision as of 15:43, 9 February 2011

Phase III: Launch

December 31st, 2011

  • Retire old site

September 1st, 2011

  • Launch new site

June 26th, 2011

  • Beta launch of new site at International Worm Meeting

Phase II: Iterative Development, Refinement, Testing

March 1st, 2011

Objective 1: conversion of all existing pages to new structure

April 1st, 2011

Objective 2: unit and UI testing in place

April 15th, 2011

Objective 3: code profiling in place


May 2nd - June 1st, 2011

Objective 4: UX testing, limited preview

June 1st, 2011

Objective 5: Production architecture

Phase I

February 1st, 2011

  • Preview new site to SAB

December 22nd, 2010

  • Begin private review of new site
  • Launch surveys on UI

July 30th - August 31st

  • Finish API development of critical classes
  • Finish migration of prominent CGI-based pages to new architecture and release into production (classic view only)
  • Solidify look-and-feel of new site: site map, browsing paths, design patterns, navigation
  • UI features to address/develop
    • Enhanced, high-performance search
    • External URL handling
    • Error trapping and reporting
    • Authorization/Authentication
    • Customizability
    • Configurable two-panel selector
    • Incorporation of old site elements like BLAST/BLAT
    • Top-level species pages (/celegans, eg) and UI clues for distinguishing them

July 14 - July 30th

  • Coronate Czars
  • Coding standards and best practices for CSS, Javascript, API in place
  • Release new pages to production powered by the new architecture (classic view only)
    • Variation, Protein, Sequence -- and maybe -- Gene
    • Todd to develop <strikethrough>deployment strategy</strikethrough>, hosting environment, and proxy configuration
    • Abby and Xiaoqi to work up templates and markup specific to the classic view
    • Norie to make requisite API changes as needed